June news and updates about Menlo’s center of campus construction project. 

June 5

The work at Stent Family Hall continues with the roofing installation, exterior lath and plaster, concrete retaining wall formwork, and exterior window installation. On the first floor, they will be painting interior sections and doing casework and tile work. Kitchen equipment installation continues this week as does interior framing and drywall on the second floor. At the Technology Center, ongoing work includes the roofing installation, interior framing and drywall, mechanical and electrical rough-in, and elevator prep.